Repulse Power Station
Repulse Dam | |
---|---|
Location of the Repulse Dam in Tasmania
|
|
Country | Australia |
Location | Central Highlands Tasmania |
Coordinates | Lua error in package.lua at line 80: module 'strict' not found. |
Purpose | Power |
Status | Operational |
Opening date | 1968 |
Owner(s) | Hydro Tasmania |
Dam and spillways | |
Type of dam | Arch dam |
Impounds | River Derwent |
Height | 42 metres (138 ft) |
Length | 433 metres (1,421 ft) |
Dam volume | 71 thousand cubic metres (2.5×10 6 cu ft) |
Spillways | 1 |
Spillway type | Uncontrolled |
Spillway capacity | 3,964 cubic metres per second (140,000 cu ft/s) |
Reservoir | |
Creates | Lake Repulse |
Total capacity | 15,900 megalitres (560×10 6 cu ft) |
Catchment area | 2,820 square kilometres (1,090 sq mi) |
Surface area | 15.3 hectares (38 acres) |
Power station | |
Name | Repulse Power Station |
Coordinates | Lua error in package.lua at line 80: module 'strict' not found. |
Operator(s) | Hydro Tasmania |
Commission date | 1967 |
Type | Conventional |
Hydraulic head | 25 metres (82 ft) |
Turbines | 1 x 29.1 MW (39,000 hp) Boving Kaplan-type turbine |
Installed capacity | 29.1 megawatts (39,000 hp) |
Capacity factor | 0.8 |
Annual generation | 153 gigawatt-hours (550 TJ) |
Website hydro |
|
[1] |
The Repulse Power Station is a conventional hydroelectric power station located in the Central Highlands region of Tasmania, Australia. The power station is situated on the Lower River Derwent catchment and is owned and operated by Hydro Tasmania.
Technical details
Part of the Derwent scheme that comprises eleven hydroelectric power stations, the Repulse Power Station is the eighth power station in the scheme. The power station is located aboveground below Lake Repulse, a small storage created by the concrete arched Repulse Dam on the Derwent River. The facilities at the Repulse Power Station are simple and include the dam, intake structure with intake gate designed to cut off full flow, a short penstock which is integral with the dam, power station building, generator equipment and associated facilities.[2][3]
Approved by the Tasmanian Parliament in 1961, the power station was commissioned in 1967 by the Hydro Electric Corporation (TAS). The station has a single Boving Kaplan-type turbine with a generating capacity of 29.1 megawatts (39,000 hp) of electricity.[4] Within the station building, the turbine has a five-bladed runner and concrete spiral casing. Pre-stressed cables passing through the stay vanes anchor the spiral casing and form part of the station foundation. No inlet valve is installed in the station. The station output, estimated to be 153 gigawatt-hours (550 TJ) annually,[1] is fed to Transend Networks’ transmission grid via two 11 kV/220 kV Siemens generator transformers to the outdoor switchyard.[2]
Water discharged from the Repulse Power Station flows into the River Derwent.[3]
See also
<templatestyles src="Stack/styles.css"/>
References
External links
- Hydro Tasmania page on the Lower Derwent
<templatestyles src="Asbox/styles.css"></templatestyles>
<templatestyles src="Asbox/styles.css"></templatestyles>
<templatestyles src="Asbox/styles.css"></templatestyles>
- Use Australian English from June 2015
- All Wikipedia articles written in Australian English
- Use dmy dates from June 2015
- Energy infrastructure completed in 1967
- Hydroelectric power stations in Tasmania
- Central Highlands (Tasmania)
- Pages with broken file links
- Hydroelectric power plant stubs
- Australian power station stubs
- Tasmania geography stubs